Project: 1-Level Addition
3726 S Street SE, Washington, D.C. 20020
Clients: karen nesmith & W. Loretta Nesmith
1-Level Addition to Include: 1 Bedroom, 1 Bathroom, 1 Closet (~500sqft total)
Pre-Construction Phase - Anticipated Timeline: 14 weeks
Relocation of plants/shrubbery in backyard
Pre-Design: Survey & field verification to verify existing conditions - plans and elevations
Schematic Design/Construction Documents (SD/CD): Floor plan for Client review.
Construction/Permit Documents (CD) 1: Final blueprints/plans submitted to DCRA
Construction/Permit Documents (CD) 2: Receive Building Permit + M/E/P Permits from DCRA
Construction/Permit Documents (CD) 3: Order materials (lumber, etc)
Construction Phase 1 - Anticipated Timeline: 2 weeks
Complete Exterior Demolition
Installation of Footers
Installation of Foundation
Installation of Crawlspace
Construction Phase 2 - Anticipated Timeline: 4-6 weeks
Installation of Framing & Roofing
Relocate Gas Meter
Installation of required plumbing & water heater (change in scope may be required depending on DCRA inspection)
Installation of new electrical (change in scope may be required for addition of HVAC)
Mechanical, electrical and plumbing inspections
Install new windows, exterior glass doors
Install new gutters
Construction Phase 3 - Anticipated Timeline: 2 weeks
Interior demolition of existing office
Installation of Insulation & Drywall
Installation of Interior Doors, Windows and all Frames
Installation of hardwood floors and baseboards
Installation of bathroom tiles, shower, toilet and vanity
Installation of exterior siding + Paint Interior
Installation of exterior slate stone patio